Fox River Dams Trunnion and Gate Repairs

Project Details

ROLE
Contractor

CONTRACT AMOUNT
$8.3 Million

OWNER
US Army Corps of Engineers – Detroit District

LOCATION
Fox River, Brown & Outagamie Counties, WI

COMPLETION
2013

Project Description

Project scope included the demolition and replacement of the lower gate piers and gates. Local cofferdams were built to facilitate the phased removal of gates and piers. 33 new concrete piers and trunnion pins were installed. 34 existing gates were removed and replaced with new. This work covered a total of four sites along the lower Fox River in Northeast Wisconsin. We were able to deliver this project one year ahead of schedule by leveraging Lunda’s marine construction resources to work on as many as three sites at the same time. Lunda partnered with USACE on this project and used the USACE RMS/QCS software to implement and control the Contractor Quality Control program that this project required.

The Fox River Dams Trunnion and Gate Repairs project received an “Outstanding” performance rating from USACE.